Mansa BMW buildings near completion

Greetings in the wonderful name of our Lord and Savior Jesus Christ.  Just wanted to update you on the upcoming BMW. We have been working tirelessly this week, despite the rains disturbing us here and there, we have made some progress. At this time we have finished the class room completely just painting and putting the doors, glass pen remaining . We have completed the floor and by next week the class room will be ready. On the dormitories we have finished plastering the inside and at the moment we are working on plastering the outside. The roofing work is also done. We are planning to finish with the plaster work next week, God willing, and start working on the floor. We are really excited and can’t wait to see our pioneer student in class. Thank you for making this possible, may the good Lord richly bless you.
In Christ service Oscar Chama. 